April Project Focus –

Reptile Fencing and Habitat Creation: Kettering, Northants.

Three Shires Ltd has sucessfully completed a large scale Reptile mitigation programme nr Kettering.

The project was completed in just 5 days and included:

  1. Installation of 2700 metres of Reptile Fencing
  2. Excavation of 6 Wetland Scraps
  3. Creation of 1 Bentonite Lined Pond
  4. Construction of 3 12 metre x 1.5 metre Hibernacula
  5. Erection of Stiles, Gates, Sinage and other Site Furniture
  6. as well as Multiple Vegetation Piles

Three Shires were originally contacted by landscape architecture practice Hankinson Duckett Associates in March. Working on behalf of Redrow Homes, HDA prodided ecological supervision of all Three Shires operations on site.

There was less than four weeks between first contact and project completion, Three Shires yet again able accomodate even the most challenging of time scales.